Ethiopia’s Ministry of Water and Energy is seeking contractors for approximately 60 kilometres of right-bank flood-protection embankment works along the Awash River in Amibara, Afar. Bids for ET-MOWE-555057-CW-RFB are due on 30 November 2026 at 3 p.m. Addis Ababa time, following the ministry’s third addendum.
This is an existing works procurement with a revised deadline. The signed extension is dated 10 November; the document’s later appearance in the ministry’s resource index does not make it a new invitation issued today.
Two lots, with a maximum of one award per bidder
Lot I covers chainage 0+200 to 35+100, while Lot II covers 35+100 to 60+000. The works include embankment construction and associated flood-protection infrastructure. The stated completion period is 450 calendar days. The ministry expects contractors to plan around seasonal river flows and prioritise critical sections.
Firms may bid for either or both lots, but a bidder can receive a maximum of one lot. Qualification is assessed for the relevant lot; bidding for two does not mean the buyer will combine the contracts into one award.
Who can compete
The consolidated clarifications confirm that this is a request for bids without a separate prequalification process. Eligible firms can submit if they meet the issued bidding document’s postqualification requirements. Those requirements cover construction experience, financial capacity, equipment, personnel and environmental and social performance.
The ministry has retained minimum average annual construction turnover of US$60 million for Lot I and US$42 million for Lot II. Its response rejects a request to lower the thresholds for local contractors. Joint ventures must follow the specified member-contribution rules; the clarifications identify at least 50% for one member and at least 30% for another for the turnover requirement.
For qualifying key activities, annual quantities may come from more than one qualifying contract, provided each project meets the required period, role and completion conditions. Road or other infrastructure experience may count where the activities and scope are substantially similar. Bidders must identify each project and provide verifiable quantities without double-counting. The detailed lot-specific thresholds remain in Section III of the bidding document.
Security and technical requirements
The published bid-security amounts are ETB80 million or US$500,000 for Lot I, and ETB54 million or US$340,000 for Lot II. The consolidated clarification specifically corrects an erroneous dollar amount raised in a bidder’s question for Lot II. Arrange the form, issuing-bank requirements and validity against the current bidding documents and latest extension.
The ministry also confirms that allocating at least 30% of total labour cost to local labour is a mandatory pass-or-fail requirement. Firms need the required environmental and social management submissions and evidence that the proposed personnel and equipment meet the tender’s requirements.
Read the amendments before pricing
Addendum 2 and the consolidated clarification package include changes to price-adjustment tables, bill-of-quantities corrections, vehicle specifications, engineer’s site facilities and additional site information. For example, the amendment removes duplicated pickup-vehicle items and changes the flood-emergency contingency item to a provisional sum.
Use the amended package together with the original documents. The ministry’s responses distinguish requests it accepted from those it rejected; a bidder’s question is not itself a change to the contract.
Where and when to submit
Submit the physical bid to the Ministry of Water and Energy, ground floor, Room 01, Haile Gebresilasie Avenue, Addis Ababa, following the technical and financial envelope instructions. Electronic bidding is not permitted. Obtain the complete documents and registration instructions through the ministry’s tender page and procurement-files directory.
The revised submission deadline is 30 November at 15:00 EAT; the announced opening is at 15:30 EAT. Addendum 3 extends bid validity through 28 March 2027. These are different milestones: the opening time is not an extra half-hour in which to deliver a bid. Check the security’s required validity against the current extension rather than copying an earlier date from the clarification history.
Keep the tender reference on the package and allow time for delivery and receipt. Contact details in the documents are for the purposes stated by the ministry; they do not turn email into an authorised bid-submission route.
For related water-sector procurement, read about the UNOPS six-town sanitation information request. More notices are in Aemero’s Tenders archive.
Photograph: Genet Alazar / Unsplash, under the Unsplash licence. The contextual image was identified by its photographer as Awash National Park; it is not a photograph of the tender’s construction site or completed embankment. Adapted in Affinity by Aemero Media.